Nebius lays out $40 billion 2027 spending plan as Microsoft site slips

On its third-quarter earnings call on Thursday, the neocloud company Nebius laid out $40 billion in planned spending for 2027, far more than Wall Street had expected. TechCrunch calls it an ambitious plan that rests on a string of planned projects already starting to show cracks. Nebius intends to fund the buildout with customer pre-payments and loans backed by customer contracts, which TechCrunch describes as essentially using the future value of its data centers to finance their construction. That can be risky if projects get bogged down by delays or cancellations. CEO Arkady Volozh told the call: "Building at this scale is hard, and delays are part of our industry right now. We are not immune."
The pressure point is Microsoft, one of Nebius's largest customers. Microsoft is paying for AI computing capacity at a data center in Vineland, New Jersey, that is now months behind schedule. The Nebius-Microsoft contract is worth up to $19.4 billion. Only just over half of the Microsoft capacity is now planned for delivery by the end of the year, with the rest coming in Q2 2027. The tranches were originally meant to be deployed in 2025 and 2026. According to Nebius's summary of the contract, Microsoft can terminate affected service after a grace period if dates are missed and no alternative capacity is offered, and the contract also includes financial penalties for late delivery. Nebius said Microsoft "has been part of the planning process" but did not say whether Microsoft has agreed to the new dates. Microsoft has not publicly canceled anything.
Chief product and infrastructure officer Andrey Korolenko said the delay arose because DataOne, the third-party operator of the site, "decided to wind down the temporary generation faster than it was expected" as the site switches to Bloom Energy fuel cells. TechCrunch adds that the switch was not entirely voluntary. In August the investigative site Floodlight identified at least 45 natural gas generators operating at the DataOne site, which had not received any permits for gas generators. New Jersey regulators fined the facility $1.1 million, finding that use of the generators violated federal law. DataOne also faces a noise-complaint lawsuit from nearby residents over a constant humming noise allegedly emitted by the data center.
The broader backdrop is a report that Microsoft is cooling on neocloud deals that are late. Bloomberg reported last week that Microsoft is tightening oversight of projects run by third parties, including Nebius, IREN and Nscale, and is debating whether it is worth signing new agreements. Per Bloomberg, Microsoft also sent employees to the New Jersey site. Bloomberg also reported that Microsoft won't use an option to more than double its Nscale agreement for a Texas data center, and recently stopped being an anchor customer for Nscale's planned Essex site after power delays. In its own quarterly report, Microsoft noted that its capex spend was lower than expected due to third-party delays. TechCrunch concludes the company is clearly not above pulling back from planned agreements where a partner misses its share of the bargain.
Nebius's case runs the other way. It says its delays come from sites it does not control, while the data centers it builds itself are coming online on time or ahead of schedule, and those will supply most of its new capacity from 2027. Chief revenue officer Marc Boroditsky said the Microsoft and Meta deals both came with significant prepayment that arrived long before delivery, and that new deals signed in Q3 came with prepayments that more than cover the cost of building the capacity behind them. Nebius ended the quarter with $7.4 billion in cash.
On financing, total prepayments plus asset-backed financing of investment-grade contracts are expected to cover up to 85% of the $40 to $45 billion 2027 capex spend. CFO Maria Del Dado Alonso Sanchez named Microsoft and Meta as contracts that can be financed this way. Boroditsky added that Nebius could "tap prepayments to shore up any additional cash requirements."
The numbers: Nebius forecast 2027 revenue of $12 to $13 billion and said it expects to break even on a pre-tax basis by the fourth quarter. Third-quarter revenue was $981 million, up 571% from a year earlier, and roughly a third of that was a one-time payment tied to a new partnership model. Nebius cut its 2026 revenue forecast by $200 million to $3 billion, citing delays at third-party sites like New Jersey. Shares ended the day down 17%. TechCrunch has reached out to Nebius, Microsoft and DataOne for comment.
Key facts
- Nebius laid out $40 billion in planned 2027 spending on its Q3 call, far more than Wall Street expected; the capex range given later is $40 to $45 billion.
- Prepayments plus asset-backed financing of investment-grade contracts are expected to cover up to 85% of that 2027 capex.
- Only just over half of the Microsoft capacity at the Vineland, New Jersey site is planned for delivery by year end, the rest in Q2 2027; the contract is worth up to $19.4 billion and allows termination after a grace period, plus late-delivery penalties.
- Q3 revenue was $981 million, up 571% year over year, with roughly a third a one-time payment; the 2026 revenue forecast was cut by $200 million to $3 billion and shares ended the day down 17%.
- Bloomberg reports Microsoft is tightening oversight of third-party projects including Nebius, IREN and Nscale and debating new agreements.
Why it matters
Nebius is testing a financing model in which customer prepayments and loans secured on customer contracts pay for the data centers that will serve those customers. TechCrunch frames it as using the future value of the data centers to fund their construction. The model works while capacity arrives on schedule. The article's point is that the plan, which was far above what Wall Street expected, rests on projects that are already slipping, and that if Nebius cannot reach capacity on time it keeps piling on costs while revenue slips.
Who it affects
Nebius investors, who saw shares end the day down 17%. Microsoft, which is paying for the New Jersey capacity and, per Bloomberg, is tightening oversight of third-party projects at Nebius, IREN and Nscale. Meta, named by Nebius as a customer whose deal came with significant prepayment. Other neocloud operators such as IREN and Nscale, which Bloomberg's reporting also touches. DataOne, the site operator, and nearby residents who brought the noise-complaint lawsuit.
How to use it
This is a reading aid for judging neocloud financing. Watch the delivery dates against the contract terms: the Microsoft tranches were meant for 2025 and 2026, the Q2 2027 date falls beyond that, and Microsoft can terminate affected service after a grace period if dates are missed and no alternative capacity is offered. Also separate what Nebius builds itself, which it says is on time or ahead of schedule and will supply most new capacity from 2027, from third-party sites it does not control.
How solid is it
The financial figures come from Nebius's earnings call as reported by TechCrunch. The contract terms are Nebius's own summary of its Microsoft contract. The Microsoft oversight, Nscale and Essex details are Bloomberg's reporting, relayed by TechCrunch, and the generator and fine details trace to Floodlight and New Jersey regulators. TechCrunch's judgment that the plan shows cracks is the author's framing, not a Nebius statement. Nebius says the delays come from sites it does not control; Nebius, Microsoft and DataOne had been asked for comment by TechCrunch.
Risks and caveats
Nebius did not say whether Microsoft has agreed to the new delivery dates, though Microsoft has not publicly canceled anything. The source does not say Microsoft has terminated service or invoked penalties. The $40 billion planned spending figure and the $40 to $45 billion capex range appear in the source without an explanation of the difference, and the source does not say how much of the spending is already financed or committed. The pre-tax breakeven is expected by the fourth quarter, with no year specified in the source. Roughly a third of Q3 revenue was a one-time payment, so the 571% growth rate overstates the underlying run rate. The source gives no reason for the 17% share drop beyond stating it happened.
“Building at this scale is hard, and delays are part of our industry right now.”
— Arkady Volozh, CEO of Nebius, on the Q3 earnings call